Deadline | Milestone |
---|---|
18.02.2013 | Project Start |
24.02.2013 | Data Collection — Complete Source Aggregation |
10.03.2013 | Data Collection — Complete Database Model Design |
24.03.2013 | Data Collection — Complete Data Extraction and Database Population |
07.04.2013 | Complete Data Analysis |
14.04.2013 | Complete Website Design |
15.04.2013 | Website Development Start |
12.05.2013 | Website Development End |
26.05.2013 | Complete Result Summarization |
27.05.2013 | Website Launch |
31.05.2013 | Project End |